Ferguson Marine eyes Port Glasgow shipyard redevelopment

The company is considering expansion options. <i>(Image: George Munro)</i>
The company is considering expansion options. (Image: George Munro)
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.

FERGUSON Marine is taking early steps towards the redevelopment of its Port Glasgow shipyard.

The company has issued a tender for ground investigation work to explore the feasibility of transforming the site, marking the first phase of a broader strategy that could see significant expansion and modernisation.

Plans include a new fabrication shed, potentially up to 100 metres long and 40 metres wide, with three floor pits up to 1.9 metres deep.

The limited space available at the yard's Newark site has long been seen as a major potential obstacle to the company's future expansion.

(Image: George Munro)

The latest move comes after Graeme Thomson, chief executive of Ferguson Marine, discussed the proposal earlier this year at Holyrood’s net zero, energy and transport committee.

He said: "You are correct that the yard will run out of space at some point.

"In the journey that we are starting on, we will look at how to optimise space so there is a proper production flow that makes best use of it."



Mr Thomson said the company was reviewing how to maximise use of its current footprint, but added that its ambitions reach beyond existing boundaries.

He said: "I have been clear since I have been in the job that I hope that Port Glasgow will not be big enough in five years."

The company is considering expanding into the Inchgreen facility, located about a mile from the current yard, as well as other nearby areas.

(Image: George Munro)

He confirmed ongoing dialogue with Inverclyde Council about these options.

He said the goal is "to get to the point at which we are creating a good solid commercial shipbuilding industry in Inverclyde again."

However, expansion presents challenges.

One complication, he explained, is that Port Glasgow's fire station sits next to the existing yard and can't be relocated.

Port Glasgow's fire station lies next door to the shipyard and presents an obstacle to expansion plans. (Image: George Munro)

Despite this, he said there is land in front of the yard that could support additional industrial development.

"It does not look like much," he said, "but it could be sufficient for us to put in another panel line or other automated equipment."

The need for expansion was raised during committee discussions about the Scottish Government’s intention to directly award contracts for four more vessels.

Ferguson Marine shipyard, Port GlasgowThe company is considering expansion options. (Image: George Munro)

Mr Thomson estimated the programme would require around five years, though the timeline depends on when contracts are finalised.

Ferguson Marine has recently completed defence work for BAE Systems, fabricating three steel hull modules for the Type 26 frigate HMS Belfast.

That contract marked the yard’s first contribution to a Royal Navy vessel.

MV Glen Rosa leaves Dales Marine in GreenockMV Glen Rosa is currently scheduled for delivery in the final quarter of 2026. (Image: George Munro)

Mr Thomson said this work demonstrates the yard’s ability to compete for major defence projects alongside its ongoing civil ferry commitments.

The firm is currently working towards the completion of the long-delayed, and vastly over-budget, CalMac ferry MV Glen Rosa - currently scheduled for delivery towards the end of this year.

In March the Scottish Government announced its intention to directly award contracts for four new ships to the yard - two smaller ferries in CMAL's Small Vessel Replacement Programme, and two fisheries research and protection ships.