MV Glen Rosa dry dock works completed ahead of schedule

Glen Rosa returned to Ferguson Marine in Port Glasgow following the completion of works at Dales Marine <i>(Image: Ferguson Marine)</i>
Glen Rosa returned to Ferguson Marine in Port Glasgow following the completion of works at Dales Marine (Image: Ferguson Marine)
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.

GLEN Rosa has returned to Ferguson Marine ahead of schedule following the completion of a programme of work in dry dock.

The ferry entered her second spell in dry dock at Dales Marine in mid-June for underwater inspections, outfitting and structural works.

She made the short journey from Port Glasgow to Greenock just a few days after her main engines were fired up for the first time.

MV Glen Rosa returing to Ferguson Marine from dry dock, July 2026 (Image: George Munro)

Glen Rosa departed dry dock on Wednesday evening to return to the shipyard for further commissioning works.

The yard will now begin a rigorous quality assurance process to test the vessel's advanced duel-fuel systems before she embarks on sea trials in the coming months.

Andrew Milligan, Executive Director of Technical at Ferguson Marine, said: "We understand how eagerly island communities are anticipating this vessel so it was vital we got this dry dock right.

“We are pleased to have been able to complete the programme of work ahead of schedule and are now focused on continuing to make steady progress ahead of sea trials to restore confidence in modern Clydebuilt standards.”

Kevin Hobbs, CEO at Caledonian Maritime Assets Limited, added: "This is welcome news, and marks another step towards the Glen Rosa joining her sister vessel on the network.”

Glen Rosa, July 2026 (Image: Ferguson Marine)

During her recent period in dry dock, marine growth was removed from Glen Rosa's hull to provide optimal conditions for sailing and improve efficiency.

All underwater coatings were renewed to protect her hull from corrosion, and her thrusters and propellers were cleaned and polished.

Bosses at Ferguson Marine say work has also progressed at a good pace on board the ferry.

While in dry dock, teams from the yard focused on outfitting the ship's interior, including painting, installing flooring, and fitting ceiling tiles and wall panels across all seven decks.

Glen Rosa, July 2026 (Image: Ferguson Marine)

Stuart McLeod, Operations Director at Dales Marine Services, added: “Leaving dry dock is always a key milestone for a vessel, and we understand the importance of the work we complete on all the vessels we support, particularly for a passenger ferry that will go on to deliver a lifeline passenger service to our Island communities.

“We’re proud to have supported Ferguson Marine with this important stage in the development of the MV Glen Rosa as she progresses towards completion and entry into service.

"Our experienced team in Greenock delivered a package of specialist works safely and efficiently, resulting in the vessel being able to leave her second dry dock ahead of schedule.”

Glen Rosa is due to be delivered to ferry operator CalMac by the end of 2026 - eight years later than originally planned.

She will undergo a hull inspection and customer review as part of the final stages before handover.