MV GLEN Rosa has successfully been relocated to deep-water facilities in Greenock this afternoon, signalling the start of a physical and digital transformation at Ferguson Marine.
The ferry departed the Port Glasgow yard shortly after midday, arriving at Inchgreen Marine Park at around 1pm.
The planned move marks a double milestone for Ferguson’s, allowing for rigorous commissioning tests to take place while giving the workforce the opportunity to prepare for the transformation of the shipyard.
Glen Rosa completed her second dry dock works at Dales Marine ahead of schedule in mid-July.
MV Glen Rosa moved from the Ferguson Marine yard to Inchgreen on Wednesday. (Image: George Munro)
She is due to be handed over to Caledonian Maritime Assets Limited later this year.
Work will now begin to create a ‘digitally enabled, state-of-the-art’ shipbuilding facility at Ferguson Marine.
Planned upgrades include the introduction of automated steel fabrication technology, electrical and safety infrastructure upgrades, and the roll-out of integrated digital management systems designed to streamline operations.
READ MORE:
Glen Rosa returns to shipyard after completing dry dock works ahead of schedule
Exclusive look inside MV Glen Rosa at Ferguson Marine as engine fires for first time
Scotrail and CalMac announce new partnership with key Inverclyde links
CalMac ferry departs Greenock to return to service - but further repairs required
CEO Graeme Thomson said: “Moving MV Glen Rosa to Inchgreen Marine Park allows us to achieve two vital strategic goals over the same time period: one focused on delivering MV Glen Rosa as quickly and efficiently as possible, and the other on preparing the yard for essential modernisation works.
“We have already undertaken modest operational upgrades over the past six months and we look forward to starting further projects that will transform Ferguson Marine into a digitally enabled shipbuilding facility.
“This will make us more competitive, putting us in a robust position to win future work, solidifying the future of the yard and shipbuilding in Inverclyde.”
(Image: Ferguson Marine)
It is anticipated Glen Rosa will be handed over in Q4 of 2026 - eight years later than her original delivery date.
Earlier this year, Ferguson Marine confirmed the cost of the ferry had increased £197.5 million.
When the order was placed for Glen Rosa and sister ship MV Glen Sannox in 2015, the ferries were expected to cost a total of £97 million.
The Glen Rosa's main starboard engine ran for the first time in June. (Image: George Munro)
Glen Rosa was launched from the Port Glasgow yard in April 2024, with her main starboard engine running for the first time in June 2026.
She is eventually destined to serve the Arran route, alongside Glen Sannox, when she joins the CalMac network - though the two vessels won't be able to use the Arran route's principal mainland terminal, in Ardrossan, until major upgrade work at the North Ayrshire port is completed following a government buy-out of the facility, which was completed in March.
The Glen Sannox has been redeployed elsewhere in the company's network as a temporary measure, and is currently operating on the service linking Skye with North Uist and Harris.